OUR PROJECTS

View our projects below, then get in touch with us

We are proud to show you our latest projects. You will find a diverse gallery of developments, remodeling, additions and new construction.

Provision of Construction, Maintenance and Civils Support Services for MLN.

May 2021 to July 2021

Client & Contractor:

PERTAMINA, Repsol, Sonatrach and Sarl CTCO.

Works Description:

CTCO will provide the following services:

  • General Maintenance & Industrial Construction Support Services.
  • Civil Work Support Services.
  • Rental Equipment.

TRAIN 4 LPG PROJECT ZCINA – HMD

Apr. 2021 to Aug. 2021

Client & Contractor:

TECNIMONT, PETROJET and Sarl CTCO.

Works Description:

SUPPLY, FABRICATION and PAINTING of the following Pipe Supports:

  • 170 Tons CS Steel Structure Pipe Supports.
  • 20 Tons LTCS Steel Structure Pipe Supports.
  • 10 Tons SS Stainless Structure Pipe Supports.

SOUTH WEST GAS FIELDS DEVELOPMENT PROJECT GAS TREATMENT UNIT (EPC2- PHASE1)

Dec.2019 To May. 2021

Client & Contractor:

L&T Hydrocarbon Engineering (LTHE).

Works Description:

  • Construction of the civil work for CPF
  • Include the following activities:
  • Earth Work
  • Concrete Work
  • Coating
  • Grouting
  • Road and Paving
  • Fence Work

Provision of Mechanical, Electrical & Instrumentation Construction Works

Dec.2019 To Jul. 2020

Client & Contractor:

In Salah Gas (ISG) / CTCO.

Works Description:

  • Construction of DSS Flow lines including civil works
  • Construction of Electrical and Instrumentation works
  • General maintenance works
  • Supply and construction of E& I works as required
  • Modification of existing facilities
  • Advanced Security enhancement works

PROVISION OF SURFACE FACILITY EPC SERVICES PHASE-4 DEVELOPMENT

Sep. 2019 – Mar. 2020

Provision Of Surface Facility Epc Services Phase-4 Development

Client & Contractor:

PERTAMINA, EPPM SA.

Works Description:

Construction of the Civil activities for the platform of Three Wells Pads:

MLNW 11P, KM06 GI and KM07 GI at MLN.

Extension of Base de VIE at Hassi Messaoud

Jun-2018 to Jun-2020

Extension of Base de VIE at Hassi Messaoud

Client & Contractor:

PERTAMINA / HOURSALEM / CTCO

Works Description:

  • Construction of Administration Building 2 Floors (846m2)
  • Construction of Laundry, Maintenance Garage and Storage Rooms (194m2)
  • Construction of Studios for Personal: 16 Senior Rooms (420m2) + 2 VIP Rooms (105m2)
  • Construction of External Works and Facilities (4873m2).
  • Construction of Law Voltage Works.

EXECUTION OF SEPARATION AND COMPRESSOR CENTRE (CSC) - SOUTH HGA

Aug. 2019 – Sep. 2020

Client & Contractor:

Sonatrach & Dodsal Engineering and Construction Ltd.

Works Description:

Construction of 138 Km pipeline
Ø 20’’ , L = 27,951 m  Ø 18’’ , L = 8,604 m
Ø 16’’, L = 31,613 m  Ø 10’’, L = 8,638 m
Ø 8’’  , L = 29,369 m  Ø 6’’  , L = 32,407 m
The activities are included all the following: Civil, Mechanical Welding, CP, and FOC.

Construction of IT Building at BDV - MLN

Mar-2019 to Feb-2020

Construction of IT Building at BDV - MLN

Client & Contractor:

PERTAMINA / HOURSALEM / CTCO

Works Description:

Construction of Informatique Building of Base De Vie – MLN.

OLEODUC G3 & G4 Ø 24’’ – 76 Km - TUNIS

Feb.2016 To Jul 2017

OLEODUC G3 & G4 Ø 24’’ – 76 Km - TUNIS

Client & Contractor:

la Société Tunisienne d’Electricité et du Gaz (S.T.E.G.) / C.T.C.O. / RETEL

Works Description:

The supply of all equipment and execution of installation and services required for the construction work, testing and pipeline commissioning. TUNIS pipeline start-Mornaguia-MABTOUH and his works.

Provision of Mechanical, Electrical & Instrumentation Construction Works

Dec.2015 To Nov. 2019

Client & Contractor:

In Salah Gas (ISG) / CTCO.

Works Description:

  • Construction of DSS Flow lines including civil works
  • Construction of Electrical and Instrumentation works
  • General maintenance works
  • Supply and construction of E& I works as required
  • Modification of existing facilities
  • Advanced Security enhancement works

Construction of Underground 8ӯ Duplex flow line for KB-17 well at KBA

Sep-2009 to Dec- 2009

Construction of Underground 8ӯ Duplex flow line for KB-17 well at KBA

Client & Contractor:

In Salah Gas / CTCO.

Works Description:

Trenching, Transportation, Laying, Field Weld, NDT & Coating, Lowering, Backfilling, Testing & Commissioning of 8ӯ Duplex flow line from Main header to KB-17 well

Construction of TEG Header and Gathering system flow lines

Dec-2009 to Nov- 2013

Construction of TEG Header and Gathering system flow lines

Client & Contractor:

In Salah Gas / CTCO.

Works Description:

Trenching, Transportation, Laying, Field Weld, NDT & Coating, Lowering, CP. Fiber Optic Cable Installation, Backfilling, Testing & Commissioning of 12”Ø Duplex flow line Header & 6”, 8” Ø Duplex Flow Lines to various wells (40 K.M Approx).

Construction of Well pads and Access Roads at KBA,TEG & REG ‐ Algeria

Nov-2010 to Oct - 2013

Client & Contractor:

BP SONATRACH and STATOIL JV & CTCO.

Works Description:

Material Procurement, Fabrication and Construction of Gas Well Heads and Miscellaneous works such as construction of Personnel camps, Offices, , Roads and Airport gypsum runways.

Algiers Refinery Rehabilitation and Adaptation Pipeline Works.

Dec-2011 to Nov- 2012

Algiers Refinery Rehabilitation and Adaptation Pipeline Works.

Client & Contractor:

SONATRACH , TECHNIP & CTCO.

Works Description:

Construction of 5 underground Pipelines Ø 26”,  16”,  10” and 6”. Trenching, Laying, Welding, NTD, Coating, Backfilling, Testing and Tie-In.

Pose d’un Réseau Injection de Gaz sur le champ de HMD

Feb-2012 to Dec- 2015

Pose d’un Réseau Injection de Gaz sur le champ de HMD

Client & Contractor:

SONATRACH & CTCO.

Works Description:

Construction of heavy wall Flow lines, 12”,  10” and 6” (32km length), the fabrication and installation of Manifolds. Trenching, Laying, Welding, NTD, Coating, Backfilling, Testing and Tie-In.

Construction of General Civil Work KBA,TEG , REG & HMN ‐ Algeria

Nov-2013 to Dec- 2014

Construction of General Civil Work KBA,TEG , REG & HMN ‐ Algeria

Client & Contractor:

BONATTI EURL.

Works Description:

Material Procurement, Fabrication and Construction of Gas Well Heads and Miscellaneous works such as construction of Personnel camps, Offices, , Roads and Airport gypsum runways.

Construction of Well pads and Access Roads at HMN

Nov-2014 to Aug-2017

Construction of Well pads and Access Roads at HMN

Client & Contractor:

PETROFAC & CTCO.

Works Description:

Construction of 20 Gas Well Heads:

  • Platform earth work, cutting & filling.
  • Concrete Works.
  • Access Roads.
  • Liners.
  • Drain Channels.
  • Fencing & Gates

CONSTRUCTION OF 24 APERTMENTS AT BLIDA

Aug-2014 to Apr-2016

Client & Contractor:

DAR ALBARAKA & {MIRI CO. and CTCO}

Works Description:

Residential buildings consist of 2 buildings, the first one is 9 floors with an area = 460 m2, the second one is 6 floors with an area = 320 m2.

Construction of 36 Apartments and a Bank branch at CHERAGA, ALGER

Dec. 2014 to Dec 2018

Construction of 36 Apartments and a Bank branch at CHERAGA, ALGER

Client & Contractor:

DAR ALBARAKA & {MIRI CO. and CTCO}

Works Description:

Bank branch (area = 335 m2), Residential building of four floors and consist of three blocks  Block A = 360 m2, Block B = 382 m2, and Block C = 497 m2.

Civil Works for KRECHBA CPF Expansion - Algeria

Feb-2008 - Jun-2010

Civil Works for KRECHBA CPF Expansion - Algeria

Client & Contractor:

BP, SONATRACH and STATOIL – JV  & PETROFAC / CTCO as a subcontractor.

Works Description:

Material Procurement & Construction of Civil works for KRECHBA CPF Expansion works at In SALAH Gas Field.

IN SALAH GAS - HMD-BDV Expansion - Algeria

Dec-2008 - Dec-2009

IN SALAH GAS - HMD-BDV Expansion - Algeria

Client & Contractor:

BP, SONATRACH and STATOIL – JV  & CTCO.

Works Description:

Material Procurement, Fabrication and Construction of Gas Well Heads and Miscellaneous works such as construction of Personnel camps, Offices, Roads and Airport runways.

Construction of Access Roads & Well pads - Algeria

2007 - 2010

Construction of Access Roads & Well pads - Algeria

Client & Contractor:

BP, SONATRACH and STATOIL – JV  & CTCO.

Works Description:

Material Procurement, Fabrication and Construction of Gas Well Heads and Allied camps.

Construction of Access Roads, Well Heads & Camps for Personnel - Algeria

2009 - 2013

Client & Contractor:

BP, SONATRACH and STATOIL – JV  & Brown And Root Condor (BRC) / CTCO as a subcontractor.

Works Description:

Material Procurement, Fabrication and Construction of Gas Well Heads and Allied camps.

Construction of TEG Header and Gathering system flow lines

2009 - 2013

Client & Contractor:

In Salah Gas / CTCO

Works Description:

Trenching, Transportation, Laying, Field Weld, NDT & Coating, Lowering, CP. Fiber Optic Cable Installation, Backfilling, Testing & Commissioning of 12”Ø Duplex flow line Header & 6”, 8” Ø Duplex Flow Lines to various wells (40 K.M Approx).

Construction of Underground 8ӯ Duplex flow line for KB-17 well at KBA

2009 - 2009

Client & Contractor:

In Salah Gas / CTCO

Works Description:

Trenching, Transportation, Laying, Field Weld, NDT & Coating, Lowering, CP. Fiber Optic Cable Installation, Backfilling, Testing & Commissioning of 12”Ø Duplex flow line Header & 6”, 8” Ø Duplex Flow Lines to various wells (40 K.M Approx).

OLEODUC LZ2, Ø 24” Pipeline - 530 Km GPL from Hassi R'mel to Arzew, Algeria)

2008 - 2009

Client & Contractor:

SONATRACH & SAIPEM Contracting ALGERIA / CTCO as a construction subcontractor

Works Description:

Mechanical construction works including Coating of 24″Ø product Pipeline -210 Km from LAGHOUAT to TIARET, Algeria.

RAS LAFFAN WOQOD HFO BUNKERING FACILITY7623413489

2006 - 2008

Client & Contractor:

QATAR PETROLEUM & Maritime Industrial Services Co. LTD. INC

Works Description:

  • 02 No of 25000 m3 Product Tanks.
  • Export P/L Ø =30’’& 20’’Length = 4.5 km.
  • Pumps Station, 03 No. of Loading Arms Installation.
  • Loops, Launchers, Receivers along with Export & Import P/L.

Water Transferring BENI HAROUN, W. MILA - Algeria

2005 - 2006

Client & Contractor:

A.N.B , Società italiana per condotte d’acqua s.p.a, & T.G.C.T.P

Works Description:

Water Transferring Pipeline, Ø 2600 mm, Ø 1600 mm, BENI HAROUN Pumping Station to Barrage OUED ATHMENIA, MILA City, Algeria.

Centre Carburant NAFTAL- AVM D.E.B – Alger Air port Houari Boumediene - ALGERIA

2005 - 2006

Client & Contractor:

NAFTAL & SECOMOC- BATENCO OUEST

Works Description:

Pipeline consists of Ø 16” & Ø 8”, Kerosene Loading Station and loading nozzle system.

CePotable Water Distribution Zone Industrial ARZEW – ORAN, ALGERIA

2004 - 2005

Client & Contractor:

SONATRACH & BENTINI spa

Works Description:

Pipeline consist of Ø 30”, Ø 20” length – 26.8 Km & Pumping Station.

MELUT OIL DEVLOPMENT Segment A2 - Sudan

2004 - 2005

Client & Contractor:

PETRODAR & STROYTRANSGAS Intl., OUAIS GROUP

Works Description:

Pipeline consists of Ø 32”, Length – 186 Km and 06 BVS, Receiver Station.

DOG1 BENI MANSOUR- SIDI ARCINE Pipeline, Algeria

2003 - 2005

Client & Contractor:

SONATRACH, Brown & Root – Condor.

Works Description:

Pipeline consist of Ø 20” Length – 90 Km.

LEODUC OZ2, Ø 34” Pipeline, 418.5 Km – Batch 01.
( PC 01 – H.E.H )To (PC05 - LAGHOUAT) – Algeria.

2002 - 2003

Client & Contractor:

SONATRACH, BRC, COSIDER.

Works Description:

Construction of 13 Block Valve Stations, (Launcher & Receiver), 5 Cut Stations & 04 Injection Points.

OLEODUC OZ2, Ø 34” Pipeline, 405 Km – Batch 02.
(PC05 - LAGHOUAT)To (ARZEW Terminal) Algeria.

2002 - 2003

Client & Contractor:

SONATRACH & STROYTRANSGAS.

Works Description:

Pipeline consist of 137 Km Ø 34”, 06 Block Valve Station & ARZEW Terminal.

CSDGL TABYIEH Gas Plant, Syria.

2001 - 2003

Client & Contractor:

CONOCO Philips (CSDGL), KVAERNER, MIS  & OUAIS Group

Works Description:

Construction of:

18” 246 km Transport Gas Pipeline

100 km, flow lines from 8” To 26”

68 km 10″ high pressure flow lines between Gas Plant and wellheads, chemical injection skids.

02 Compressor Stations

Gathering Station at JAFRA, QAHAR

LPG Railway Loading stations.

Condensate & fire water storage Tank.